Tošanovice-Žukov Bridge, Czech Republic

Информация по проекту

Расположение: Ostrava, Чехия

Design: steel composite bridge
Length: 720 m

Требования

The strut axes open out from 6.50 m to 9.00 m in the centre of the bridge.

Клиент

Metrostav a.s., Division 4, Prague

Преимущества для клиента

  • flexible connecting possibilities for steel walers, scaffold tubes, heavy-duty spindles and tie rods
  • can be adapted to various main beam spacings
Martin Šimek, Site Manager
Martin Šimek
Site Manager

The erection of steel composite bridges is considerably easier and much faster with the PERI formwork carriage construction.

PERI-решение

Two modular formwork carriages from the VARIOKIT system